The Project Involved the Supply, Installation, Testing, and Commissioning (SITC) of a 220KV Overhead Transmission Line for Evacuation of Power from a 200 MW Project under GUVNL at Faredi Village. The Key Challenges included Execution in Compliance with GUVNL Technical Specifications, Managing Right of Way (ROW) in a Populated Area, Ensuring Structural and Electrical Safety at Extra-High Voltage Levels, and Coordinating Line Charging with the State Transmission Utility. Maintaining Construction Quality, Safety Standards, and Adherence to Tight Timelines were Critical Due to the Project’s Grid Integration Requirements.